Documentation Error with Resource Scheduling Methods

PSS ID Number: Q71118 Article last modified on 11-16-1994

1.00

WINDOWS

The information in this article applies to:
- Microsoft Project for Windows, version 1.0

SUMMARY

Page 398 of the “Microsoft Project for Windows Reference” manual has a documentation error. There is a table that shows what happens to the duration of a task when you change the work for the resource that is assigned to the task. “Increase” and “Decrease” are listed in reverse order.

The table should read as follows:

If You Change the Units for And Units The Task Duration ————————— ——— —————–

A single resource driving Decrease Changes to the work per unit of the duration this resource

                          Increase    Changes to the largest work per
                                      unit of the resources assigned

One of multiple resources Decrease Changes to the work per unit of driving the duration this resource

                          Increase    Does not change because other
                                      resources drive the task
                                      duration

A resource not driving the Decrease Changes to the largest work per task duration unit of the resources assigned

                          Increase    Does not change because other
                                      resources drive the task
                                      duration

MORE INFORMATION

The table appears as follows in the “Microsoft Project for Windows Reference” manual:

A single resource driving Increase Changes to the work per unit of the duration this resource

                          Decrease   Changes to the largest work per
                                     unit of the resources assigned

One of multiple resources Increase Changes to the work per unit of driving the duration this resource

                          Decrease   Does not change since other
                                     resources drive the task
                                     duration

A resource not driving the Increase Changes to the largest work per task duration unit of the resources assigned

                          Decrease   Does not change since other
                                     resources drive the task
                                     duration