PRJ2000: Incorrect Work Variance Value in Microsoft Project Central

Article ID: 282787

Article Last Modified on 1/29/2007



APPLIES TO

  • Microsoft Project 2000 Standard Edition



This article was previously published under Q282787

SYMPTOMS

In Microsoft Project Central, when you apply the Work details on the View Your Portfolio page, the Work Variance value may not match the value in the Project Summary Task for the same project in Microsoft Project 2000.

RESOLUTION

To resolve this problem, obtain Microsoft Project 2000, Service Release 1 (SR-1).

To obtain SR-1, click the article number below to view the article in the Microsoft Knowledge Base:

288953 PRJ2000: How to Obtain and Install Microsoft Project 2000 SR-1


STATUS

Microsoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
This problem was corrected in Microsoft Project 2000, Service Release 1 (SR-1).