Microsoft KB Archive/193315

From BetaArchive Wiki
Knowledge Base


PRJ98: Finish Dates Are Too Early After Using Adjust_Dates Macro

Article ID: 193315

Article Last Modified on 1/23/2007



APPLIES TO

  • Microsoft Project 98 Standard Edition



This article was previously published under Q193315

SYMPTOMS

In Microsoft Project 98, when you use the Adjust Dates macro to reschedule tasks in a project that is scheduled from finish, the finish dates for all tasks in the project may be a day earlier than expected.

CAUSE

This behavior may occur when you run the Adjust_Dates macro and the following conditions are true:

  • One or more tasks are assigned a Must Start On constraint, Must Finish On constraint, or Finish No Later Than constraint.


  • The project is scheduled to Start From Finish.


  • When you run the Adjust_Dates macro, you enter a new project finish date without a finish time in the Adjust Dates dialog box.

If you do not include a finish time with the new project finish date, the macro uses the Default Start Time setting (8:00 A.M. for example) on the Calendar tab in the Options dialog box.

WORKAROUND

To work around this behavior, when you run the Adjust_Dates macro, include the finish time with the new finish date, for example 9/25/98 5:00 PM.

STATUS

Microsoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.

Keywords: kbbug kbpending KB193315