Microsoft KB Archive/178678

From BetaArchive Wiki
Knowledge Base


PRJ98: Resource Time-Phased SV Does Not Equal Resource Total SV

Article ID: 178678

Article Last Modified on 1/22/2007



APPLIES TO

  • Microsoft Project 98 Standard Edition



This article was previously published under Q178678

SYMPTOMS

In Microsoft Project 98, in the Resource Usage view, you may see that a resource time-phased Schedule Variance (SV) does not equal the total SV values for the resource.

CAUSE

This behavior occurs when the following conditions are true:

  • The resource was assigned to more than one task.


  • A cost is assigned to the resource.


  • At least one task that the resource was assigned to was deleted.

Resource time-phased SV values are using the rolled up assignments Budgeted Cost of Work Scheduled (BCWS) values instead of the resources BCWS values.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, click the article number below to view the article in the Microsoft Knowledge Base:

185102 PRJ98: How to Obtain and Install MS Project 98 SR-1



Additional query words: scheduled s v

Keywords: kbbug kbpending KB178678