Article ID: 177015
Article Last Modified on 1/22/2007
APPLIES TO
- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
This article was previously published under Q177015
SYMPTOMS
In Resource Usage view in Microsoft Project, if you drag an Actual Cost to a new day, the cost will move to the new day and the original day's Actual Cost will change to zero. If you then delete the zero Actual Cost, it will be split incorrectly between the original day and the new day.
CAUSE
This problem occurs when you move an Actual Cost for a task and then attempt to delete the zero value of Actual Cost if the Actual Costs is Always Calculated by Microsoft Project option is turned off. To locate this option, click Options on the Tools menu, and then click the Calculation tab.
WORKAROUND
To work around this problem, follow these steps:
- Select the Actual Cost for the assignment.
- On the Edit menu, click Cut.
- Click where you want to move the cost.
- On the Edit menu, click Paste.
The original location will be blank.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.
Additional query words: prj2000
Keywords: kbbug kbpending KB177015