PRJ: Task Split Information Not Saved When Using Work Contour

Article ID: 171394

Article Last Modified on 1/20/2007



APPLIES TO

  • Microsoft Project 2000 Standard Edition
  • Microsoft Project 98 Standard Edition



This article was previously published under Q171394

SYMPTOMS

When you change the contour of a resource assignment, task split information is not preserved.

CAUSE

Microsoft Project does not track task split information if a contour is chosen for a task.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.


Additional query words: prj2000

Keywords: kbprb kbusage KB171394