Summary task Work/Cost different on crosstab reports

Article ID: 130391

Article Last Modified on 1/31/2007



APPLIES TO

  • Microsoft Office Project Professional 2007
  • Microsoft Office Project Professional 2003
  • Microsoft Project 2002 Standard Edition
  • Microsoft Project 2000 Standard Edition
  • Microsoft Project 98 Standard Edition
  • Microsoft Project 4.1 Standard Edition
  • Microsoft Project 4.1a
  • Microsoft Project 4.0 Standard Edition
  • Microsoft Project 4.0 for Macintosh



This article was previously published under Q130391

SYMPTOMS

In Microsoft Project, when you print or print preview a crosstab report, summary task Cost or Work may be less than what is displayed for that summary task in a task view.

CAUSE

Summary Cost and Work is calculated differently in a crosstab report than it is in a task report or task view. In a crosstab report, Cost for a summary task includes only Fixed Cost and cost for resources assigned to the Summary Task itself. It does not include the total of its subtasks. Additionally, Summary Task Work includes only Work for resources that are assigned to that Summary Task.

Hours that are not assigned to a resource will not appear in the crosstab report. Therefore, the crosstab report will show nothing for the Summary Task if the Work and Cost are assigned to the subtasks. If the subtasks are shown in the report (that is, if the Summary task is expanded to show the subtasks), the report will show Assigned Work and Fixed Costs.


Additional query words: prj2000 PRJ prj2002 prj2003 prj2007