Project: Individual Resource Calendars Do Not Update Costs PSS ID Number: Q70926 Article last modified on 04-08-1991 PSS database name: D_PRoject

4.00

MS-DOS

Summary:

If an activity has a resource that is using an individual resource calendar, costs and demand usage may not be updated even when entering Y after receiving the “Enter Y to recalculate” prompt.

Microsoft has confirmed this to be a problem in Project version 4.00. We are researching this problem and will post new information here as it becomes available.