Must Enter Resource Cost Twice When Entering New Resource Info
PSS ID Number: Q70631 Article last modified on 11-16-1994
1.00 3.00
WINDOWS
The information in this article applies to: |
- Microsoft Project for Windows, versions 1.0, 3.0 |
SUMMARY
When using the Resource Form’s Resource Cost to enter units of 0 and a specific cost for a new resource, the cost field must be entered twice.
MORE INFORMATION
Steps to Reproduce Behavior
- From the View menu, choose Task Entry with the Task Form as the bottom pane.
- Enter a task name in the top pane.
- Select the lower pane.
- From the Format menu, choose Resource Cost.
- Enter a new resource name in the task entry form.
- Enter the units as 0 (useful for nonhuman or one-time costs).
- Enter a value of $10.00 in the Cost field and press ENTER.
- A message will appear advising you that the resource does not exist, and asks if you want to create it. Select Yes.
- Enter a cost per use of $10.00 and choose OK.
You will be returned to the task entry form, but the cost will be $0.00. Type the amount desired a second time and the cost will update to the field.
REFERENCES
“Microsoft Project for Windows Reference,” Version 1.00. “Costing,” pages 43-50, 356-357, 460.
KBCategory: kbusage kbprb KBSubcategory:
Additional reference words: 1.0 1.00 3.0 3.00