Project: Individual Resource Calendars Do Not Update Costs PSS ID Number: Q70926 Article last modified on 04-08-1991 PSS database name: D_PRoject
4.00
MS-DOS
Summary:
If an activity has a resource that is using an individual resource calendar, costs and demand usage may not be updated even when entering Y after receiving the “Enter Y to recalculate” prompt.
Microsoft has confirmed this to be a problem in Project version 4.00. We are researching this problem and will post new information here as it becomes available.