SYMPTOMS

A task that is set to 100% complete does not show the complete indicator next to the task.

CAUSE

This behavior occurs when you set a task to 100% complete and then change the Actual Finish date to NA. Although the task remains 100% complete, the complete indicator will be removed.

WORKAROUND

To work around this problem, and show the complete indicator for the task, do either of the following:

  • Re-enter the task as being 100% complete.


-or-

  • Enter an Actual Finish date for the task.