PRJ: Actual Cost and Remaining Cost Show Unexpected Value

Article ID: 169388

Article Last Modified on 1/19/2007



APPLIES TO

  • Microsoft Project 98 Standard Edition
  • Microsoft Project 3.0 Standard Edition
  • Microsoft Project 4.0 Standard Edition
  • Microsoft Project 4.1 Standard Edition
  • Microsoft Project 3.0 for Macintosh
  • Microsoft Project 4.0 for Macintosh



This article was previously published under Q169388

SYMPTOMS

If you assign a negative fixed cost to a task that has no resource assigned to it, the actual cost will reflect the negative cost and the remaining cost will be zero, even when the percentage completed equals zero.

CAUSE

If the task has not started, the actual cost is zero and the remaining cost is the full cost of the task. When the task is completed, the remaining cost will be zero, and the actual cost will be the full cost of the task.

Keywords: kbprb kbusage KB169388