Microsoft KB Archive/837240

From BetaArchive Wiki
Knowledge Base


Description of Project 2003 Service Pack 1

Article ID: 837240

Article Last Modified on 9/30/2007



APPLIES TO

  • Microsoft Office Project Professional 2003
  • Microsoft Office Project Standard 2003



SUMMARY

Microsoft has released a service pack for Microsoft Office Project 2003 . This article describes the following items about the service pack:


INTRODUCTION

Microsoft Office Project 2003 Service Pack 1 (SP1) provides the latest updates to Microsoft Office Project 2003. Project 2003 SP1 contains significant security enhancements, as well as stability and performance improvements. Some of the fixes that are included with Project 2003 SP1 have been previously released as separate updates. This service pack combines them in to one update.

MORE INFORMATION

Service pack details

List of issues that this service pack fixes

The Project 2003 SP1 fixes the issues that are described in the following hotfix packages:

834706 Description of Microsoft Office Project 2003 hotfix package: January 22, 2004


835705 Description of the Microsoft Office Project 2003 hotfix package: February 27, 2004


838026 Microsoft Office Project 2003 hotfix package: March 15, 2004


838879 Microsoft Project 2003 hotfix package: March 23, 2004


832887 Description of the Microsoft Office Project 2003 Update: March 23, 2004


839631 Microsoft Office Project 2003 hotfix package: April 1, 2004




The Project 2003 SP1 fixes the issues that are described in the following Microsoft Knowledge Base articles:

840376 Actual Work that is submitted by the local resources may be lost when you synchronize a project that uses Protected Actuals and local resources in Project 2003


839632 Finish date of project plan may change in Project 2003


840314 Task data may disappear or value custom field values in a task may be missing when you make changes to enterprise custom fields in your Master Project File in Project 2003


839636 Assignment delays change the Finish date of a project plan in Project 2003




The Project 2003 SP1 fixes the following issues that were not previously documented in the Microsoft Knowledge Base.

The Smart Tag information is incorrect when you increase or decrease a task duration



When you increase or decrease the duration of a task in the Spanish-language version of Project Professional 2003, the Smart Tag displays the same incorrect information.


The Project window does not display color when you use a non-Windows XP theme



If you run Project 2003 on a Microsoft Windows XP-based computer with a non-Windows XP theme, the active window does not display color to indicate that it is the active window when you open multiple Project windows.


Changes to a new task that were created by a resource are not updated to the resource's timesheet



When a resource submits changes to a new task that the resource created, the changes are not updated to the resource's timesheet.


Base-line information is redistributed when actual work is submitted for more than one non-working day



If you submit actual work for more than one non-working day, the base-line information may be redistributed to working days.


Free Slack and Total Slack values are incorrect after you change the Lag time to a negative value



When you change the Lag time of a successor task to a negative value, the Free Slack and Total Slack values are incorrect.


Project codes are not saved when you import multiple projects



If you use the Import Project Wizard to import a series of projects, the values that you set for Project codes on the first project also appear for each subsequent project that you import. However, these values are not saved with each project.


You receive an error message when you use the Import Resources to Enterprise option



If you use the Import Resources to Enterprise option in Project 2003, you receive the following error message when you try to click Standard in the Base calendar drop-down box in the Import Resources Wizard:

This value is not valid in this situation.
Check the field to see if it requires text, a date, or a number, and that you typed the information correctly.



You receive the "Invalid entry" error message when you import data from Microsoft Excel



When you import data from an Excel spreadsheet that contains a date that was entered in such a way that Excel automatically changed the format of the date from General to Custom, you receive an error message that indicates that the value is not a valid entry.


Project 2003 quits unexpectedly when you export data to Microsoft Visio in the landscape page orientation



When you export Project data to Visio in the landscape page orientation, Project 2003 may quit unexpectedly.


The Remain Cost field is incorrect when you add it in a header, in a footer, or in a legend



If you add the Remaining Cost field to a header, to a footer, or to a legend and then either preview the page or print the page, the cost information does not appear correctly, and it is incorrectly mapped to the Remaining Work field. For example, the Remaining Cost field may appear as "0h" instead of the expected "$0."


You receive an error message when you compare your project to your published project



When you click Compare Project Versions on the Compare Project Versions toolbar to compare your project with your published project, you receive an error message.


Non-language characters appear in the Warning dialog box when you unlink Risks in a non-English version of Project 2003



If you click to clear the Link Risks check box in a non-English version of Project 2003, and then you save the changes, the Warning dialog box may appear with non-language characters.


Project 2003 quits unexpectedly if you save an Enterprise project plan that contains the characters "pwd” as part of the file name



If you save an Enterprise project plan that contains the characters "pwd” as part of the file name, Project 2003 quits unexpectedly.


The Outline Codes lookup table is damaged when you paste it in an Enterprise project plan



If you paste Outline Codes from one Enterprise project plan to another Enterprise project plan, the pasted Outline Codes lookup table may be incomplete and damaged.


The graphical indicator does not appear in Project Web Access when you use the Contains or Contains exactly options



If you use a graphical indicator in an Enterprise project plan that uses the Contains or the Contains exactly options, the graphical indicator will not appear in your project plan in Project Web Access (PWA).


The Actual Work and Remaining Work fields are not calculated in the Timesheet view



If you track a project by percent complete (% Complete), and the Actual Work field and the Remaining Work field are not in the Timesheet view, the Actual Work field and the Remaining Work field are not calculated when updates are submitted to the project manager.


Changes are lost in the Outline Codes lookup table after you make changes to the table mask



When you make changes to an Outline Code lookup table in your Enterprise project plan and then make changes to the table mask, the changes that you made to the Outline Code lookup table may be lost and the editing features of the table do not function as expected.


The Enterprise global template is restored as a published project plan



When you restore a backup copy of your Enterprise global template, the template may be restored as a published project plan.


The Project Working Time text is translated incorrectly in the Korean-language version of Project 2003



When you click Tasks on the Project Guide toolbar, and then click Define general working times on the Tasks task pane in the Korean-language version of Project 2003, the text under Hints is translated incorrectly in the Korean language.


You receive an invalid entry error message when you use the "is within" option for a graphical indication in the Chinese (Simplified) version of Project 2003



When you try to use the is within option for a graphical indicator for a custom field in the Chinese (Simplified) language version of Project 2003, you receive the following error message:

The entry is not valid. Please click the entry in the list, then press Enter.



You receive a logon prompt to Project Server behind Project 2003 splash screen



When you open a project plan that resides on a Microsoft Windows SharePoint Service site that uses Basic Authenticity, the logon prompt appears behind the Project 2003 splash screen.


An incorrect value is selected in the Resource Information dialog box for a custom field that contains a value list



When you try to click a value for a custom field that contains a value list on the Custom Fields tab, an incorrect value is selected.


Indented tasks lose their indentation when you import data to the active project



When you use the Merge the data into the active project option in the Import Wizard to import a file, such as an Excel file, to your project plan, some indented tasks may lose their indentation.


Base-line information is redistributed when actual work is submitted for a nondefault working time



If you submit actual work for a day, such as Saturday, that is set as non-default working time, the base-line information may be redistributed to other working days when you reopen the project plan.


The 7 AM hour missing in the Project Working Times wizard in the French-language version of Project 2003



When you click 24 Hours in the Project Working Times wizard in the French-language version of Project 2003, the 7 AM hour may be missing.


A blank object is inserted when you paste a Project document object in Microsoft Word



When you try to paste a Microsoft Project document object in a Microsoft Word document, a blank object is inserted instead of the Project document object.


Performance improvement when you click to select the Connecting across a WAN (limited functionality in Build Team) check box



When you start Project Professional 2003, a Project Server Accounts dialog box appears with a check box that is titled Connecting across a WAN (limited functionality in Build Team). If you click to select the Connecting across a WAN (limited functionality in Build Team) check box, it effectively tells Project 2003 not to read summary resource assignments when it displays the Build Team dialog box.

As a performance improvement in Project Professional 2003 Service Pack 1, when you click to select theConnecting across a WAN (limited functionality in Build Team)check box, the summary resource assignments will not be available in the Resource Usage view or in the Build Team dialog box.


Text that is in the Options dialog box is in the English-language in the German-language version of Project 2003



When you view the Options dialog box in the German-language version of Project 2003, some of the dialog box text is in the English-language instead of being in the German-language. This issue occurs on the following tabs in the Options dialog box:

  • General
  • Edit
  • Schedule
  • Calculation
  • Save



A new assignment that is created by a resource causes a duplicate assignment, and with Project 2003 quits unexpectedly



When a resource creates a new assignment on an existing task, a duplicate assignment may be created. This action may cause Project 2003 to quit unexpectedly.


You receive an error message indicating to type time with a "h" in the German-language version of Project 2003



If you install the German Multilingual User Interface Pack in Project 2003, you receive an error message indicating to type the time with a "h" when you type an hour value in the duration column for a task. For example, you receive an error message stating that you must type 8h in the duration column for a task.


Assert error message occurs after the project manager updates cleared actual work values



If an enterprise resource uses PWA to clear (backspace over) actual work values that were previously submitted and then submits the cleared values to the project manager, an Assert error message occurs when the project manager processes the update and then inserts the Actual Work field and the Actual Work Protected field in the Task Usage view.


The Timesheet view of the Actual Work field and the Work field display incorrect values before you update the Timesheet view



When you add the Actual Work field and the Work field to the Timesheet view in PWA, the values for the Actual Work field and the Work field are incorrect until you update the view.


The Earned Value Method and the Physical % Complete fields are missing in PWA



When you manage the Earned Value Method view in PWA, the Earned Value Method and the Physical % Complete fields are missing.


You cannot change the custom date field to NA after the project has been saved to Project Server

After you type a date in a custom date field and save your project to your Project Server, you cannot change the custom date field back to NA.


You receive a message when you save a project plan if there is a long note in the Project Summary task



If you type a long note in the Project Summary task in Project 2003 and then try to save the project plan, you may receive the following message:

There are multiple lines of text in the existing note. If you change the note here, all lines of text except the first line, and all formatting, will be removed. If you do not want to lose any text or formatting, edit notes by clicking the Notes button on the standard toolbar. Do you want to change the note anyway?




The Work field increases in value when you click Synch to Protected Actuals



When you click Synch to Protected Actuals in Project Professional 2003, the Work field may increase for individual tasks and for Project Summary tasks.


Baseline data is corrupted in the Resource Usage view in Project 2003



When you insert a baseline in the Resource Usage view, the data for the baseline may be corrupted and may cause cube errors.


You receive an error message when the project manager updates a project plan that contains a duplicate assignment task



When a project manager tries to update a project plan in PWA that contains an unpublished duplicate assignment task that they assigned to themselves, the project manager receives the following error message:

The message could not be opened because it contains an attachment in a format that cannot be read.




The Work field and the Duration field for Assignments are "out of synch" in the Task Usage view



When you try to use Synch to Protected Actuals in Project Professional 2003, the Work field and the Duration field for Assignments may be "out of synch" in the Task Usage view.


The Finish date moves to a later date every time that you click Synch to Protected Actuals in Project 2003



Every time that you click Synch to Protected Actuals in Project Professional 2003, the Finish date of the task moves out to a later date.


Actuals move to a different day when the project manager updates the project plan in Project 2003 after changing the Assignment Delay



When a project administrator sets the Protected Actuals option in PWA, sets an Assignment Delay in Task Usage view in Project Professional 2003, and then publishes the project plan, the actuals may be placed (moved) to different days if the Assignment Delay is changed again in Project 2003 after the project manager updates the actuals.


The Synch to Protected Actuals option causes the Finish date to change for split task in Project 2003



When you click the Synch to Protected Actuals option in a project plan that contains a split task in Project 2003, the Finish date may change.


The Work field values that are in the Task Usage view in Project 2003 do not match



After a project manager updates only the recent tasks submitted, the Work field values in the Task Usage view in Project 2003 may not match.


Unexpected date changes when you use the Week date format in Project 2003

When you use the Week date format in the Timescale of Project 2003 option, you receive unexpected date changes.


The Export Grid to Excel feature in PWA causes an error message, and Excel keeps running in the background



When you try to export a project plan that contains more than eight outline levels using the Export Grid to Excel feature in PWA, a hidden instance of Excel remains running, and you receive the following error message:

An error occurred while exporting the grid data to Excel. Because of this error, you can only copy XML data to the Clipboard. Do you want to continue?


Earlier released updates that are included in this service pack

The Project 2003 Service Pack 1 includes the following earlier released update:

832887 Description of the Microsoft Office Project 2003 update: March 23, 2004


Additional improvements in Project 2003 SP1

For more information about what is different about Project 2003 after installing Project 2003 Service Pack 1, click the following article number to view the article in the Microsoft Knowledge Base:

843608 How to let Project Professional 2003 connect to your Project Server that is located in the intranet zone without being prompted to add the Project Server as a trusted site


Known issues

Known issues during installation of the service pack

When you use the IExpress /q switch during setup, the switch does not function as expected



When you use the /q switch during setup, the switch does not function as expected. For example, the following setup command does not work as expected, and prompts are not suppressed:

/c: ohotfix.exe /q


To use the /q switch during setup, you must use the following format:

/c:"ohotfix.exe /q" /q


Known issues that may occur after the service pack is installed

There is a known issue that may occur after you install Project 2003 SP1. For additional information about the known issue after you install Project 2003 SP1, click the following article number to view the article in the Microsoft Knowledge Base:

873125 You cannot remove Service Pack 1 for Office 2003 products


Installation details

How to obtain and install the service pack

Project 2003 SP1, and also installation instructions and deployment strategies, are found on the Microsoft Download Center. To download this service pack from the Microsoft Download Center, visit the following Web site:

How to determine whether the service pack is installed

The service pack contains an updated version of the following file:

   File name      Version
   --------------------------
   Winproj.exe    11.1.2004.1707

You do not have to install this service pack if you have a later version of the files that are listed in the previous table. For additional information about how to determine the version of Microsoft Office Project 2003 that is installed on your computer, click the following article number to view the article in the Microsoft Knowledge Base:

821549 How to check the version of Office 2003 products




Additionally, the following files are also installed when you install Project 2003 SP1:

   File Name
   ------------
   Alrtintl.dll   
   Oinfo11.ocx
   Atlconv.dll   
   Oinfop11.mof
   Compprj.dll    
   Osa.exe
   Cpicoff.dll    
   Owc10.dll
   Dwdcw20.dll   
   Owc11.dll
   Dwtrig20.exe   
   Owci10.dll
   Epsimp32.flt   
   Owci11.dll
   Fm20.dll       
   Owsclt.dll
   Fpsrvutl.dll  
   Pj11od11.dll
   Fpwec.dll     
   Pj11tm11.dll
   Gdiplus.dll   
   Pjintl.dll
   Gdiplus.dll    
   Pjintlc.dll
   Ieawsdc.dll    
   Pjoledb.dll
   Intlband.htm  
   Prjres.dll
   Msconv97.dll  
   Riched20.dll
   Mso.dll       
   Setlang.exe
   Msohelp.exe    
   Slintl.dll
   Msointl.dll   
   Usp10.dll
   Msxml5.dll     
   Vbe6.dll

MSP file information for administrators

The administrative update is made up of a full-file Windows Installer patch file (MSP file) that is packaged in an executable file. The following MSP files are distributed in this service pack:

Language MSP file name
Brazilian Portuguese Project2003-KB837240-fullfile-ptb.msp
Chinese Simplified Project2003-KB837240-fullfile-chs.msp
Chinese Traditional Project2003-KB837240-fullfile-cht.msp
Czech Project2003-KB837240-fullfile-csy.msp
Danish Project2003-KB837240-fullfile-dan.msp
Dutch Project2003-KB837240-fullfile-nld.msp
English Project2003-KB837240-fullfile-enu.msp
Finnish Project2003-KB837240-fullfile-fin.msp
French Project2003-KB837240-fullfile-fra.msp
German Project2003-KB837240-fullfile-deu.msp
Greek Project2003-KB837240-fullfile-ell.msp
Hebrew Project2003-KB837240-fullfile-hbr.msp
Hungarian Project2003-KB837240-fullfile-hun.msp
Italian Project2003-KB837240-fullfile-ita.msp
Japanese Project2003-KB837240-fullfile-jpn.msp
Korean Project2003-KB837240-fullfile-kor.msp
Norwegian Project2003-KB837240-fullfile-nor.msp
Portuguese Project2003-KB837240-fullfile-ptg.msp
Russian Project2003-KB837240-fullfile-rus.msp
Spanish Project2003-KB837240-fullfile-esn.cab
Swedish Project2003-KB837240-fullfile-sve.msp
Turkish Project2003-KB837240-fullfile-trk.msp

Features for reinstalling specific components for administrators

If you update your administrative installation point and recache and reinstall Project 2003 SP1 on client computers, we recommend that you run a command line that includes the REINSTALL=ALL property to install all features.

For detailed procedures to patch an administrative image and update client computers, see the "Updating clients from a patched administrative image" section in the "Distributing Office 2003 Product Updates" topic. To view the "Distributing Office 2003 Product Updates" topic, visit the following Microsoft Web site:

The Office Admin Update Center for Office IT Professionals contains the latest administrative patches and strategic deployment resources for all versions of Office. For more information about the Office Admin Update Center, visit the following Microsoft Web site:

Project 2003 Service Pack 1 for Multilingual User Interface Pack details

The Project 2003 Service Pack 1 for Multilingual User Interface Pack provides the latest updates to the Microsoft Office Project 2003 Multilingual User Interface Pack. The Project 2003 Service Pack 1 for Multilingual User Interface Pack makes sure that Project 2003 performs with complete functionality when you use the Project 2003 Multilingual User Interface Pack.

For additional information, visit the following Microsoft Web site:

Error signature details

You may receive an error message that is similar to the following when you use Project 2003:

Microsoft Office Project has encountered a problem and needs to close. We are sorry for the inconvenience.

To see what data this error report contains, click here.

When you view the data in the error report, the report contains an error signature that is similar to one of the following error signatures:

 
   Application name  Application version  Module name   Module version  Offset
   -----------------------------------------------------------------------------
   Winproj.exe       10.0.2002.502        Winproj.exe   10.0.2002.502   00187aeb
   Winproj.exe       11.0.2003.816        Winproj.exe   11.0.2003.816   0065afcf
   Winproj.exe       11.0.2003.816        Winproj.exe   11.0.2003.816   001880d6
   Winproj.exe       11.0.2003.816        Winproj.exe   11.0.2003.816   00250ac3
   Winproj.exe       11.0.2003.816        Winproj.exe   11.0.2003.816   001df0f5
   Winproj.exe       11.0.2003.816        Vbe6.dll      6.4.99.69       0012fa30
   Winproj.exe       11.0.2003.816        Winproj.exe   11.0.2003.816   001deb0f
   Winproj.exe       11.0.2003.816        Winproj.exe   11.0.2003.816   0029eef3
   Winproj.exe       11.0.2003.816        Pj11od11.dll  11.0.2003.816   000261cc

Additionally, other program versions, module versions, and offsets are possible.

Keywords: kbtshoot kbfix kbservicepack kbupdate kbmui atdownload KB837240