Microsoft KB Archive/57486

From BetaArchive Wiki
< Microsoft KB Archive
Revision as of 18:56, 18 July 2020 by 3155ffGd (talk | contribs) (importing KB archive)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

Costs Not Prorated After Change to Work

PSS ID Number: Q57486 Article last modified on 03-15-1995

1.00 3.00 | 1.10 3.00

WINDOWS | MACINTOSH

The information in this article applies to:
- Microsoft Project for Windows, versions 1.0, 3.0 - Microsoft Project for the Macintosh, versions 1.1, 3.0

SUMMARY

If a task has been assigned a resource, and the rates for that resource are prorated, any changes to cost values after remaining work has been set to 0 (zero), are added to or removed from the last work period for the resource.

MORE INFORMATION

A 10-day task that has been assigned a single resource whose rate is $10/hour has a work value of 80 hours, assuming default working hours. The total cost for the resource, using the formula Work*Rate is $800. If remaining work is set to 0 (actual becomes 80 hours), and the resource cost value is set to $900, then the Resource Usage view, using the Cost format, displays the costs as follows:

Day: 1 2 3 4 5 6 7 8 9 10 Cost: 80 80 80 80 80 80 80 80 80 180

This extra amount on day 10 results because any edits to the cost field after remaining work has been set to 0 take place on the last working period. Therefore, the additional $100 is added to the last period, setting the last day to $180.

Conversely, if the cost is adjusted downward to $600, the costs appear as follows:

Day: 1 2 3 4 5 6 7 8 9 10 Cost: 80 80 80 80 80 80 80 80 80 (120)

KBCategory: kbother KBSubcategory:

Additional reference words: 1.0 1.00 1.1 1.10 3.0 3.00

Copyright Microsoft Corporation 1995.