Milestones Not Displaying in Gantt Chart

PSS ID Number: Q46146 Article last modified on 03-15-1995

1.00 3.00 3.00a 4.00 | 1.10 3.00 4.00

WINDOWS | MACINTOSH

The information in this article applies to:
- Microsoft Project for Windows, versions 1.0, 3.0, 3.0a, 4.0 - Microsoft Project for the Macintosh, versions 1.1, 3.0, 4.0

Milestone tasks are drawn on the default Gantt palette from Scheduled Finish to Scheduled Finish. If the definition is changed to Scheduled Start (SS) to Scheduled Finish (SF), the task marker is not visible on the Gantt Chart. This is because 0 (zero) duration tasks (milestones) that are set to be drawn from SS to SF are interpreted as null tasks and, therefore, are not drawn.