Definition of Early Finish Date in Project for Windows PSS ID Number: Q46141 Article last modified on 03-27-1992 PSS database name: W_WinPRoj

1.00 3.00 | 1.10

WINDOWS | MACINTOSH

Summary:

The early finish date represents the estimated time the task finish date will occur if the preceding task ends as early as possible. Microsoft Project for Windows and Macintosh calculates the early finish date by adding a task’s early start date and the task’s duration.

Additional reference words: 1.0 1.00 1.1 1.10 3.0 3.00 mpf