Project for Windows Allows Duplicate Task Names
PSS ID Number: Q44587 Article last modified on 03-15-1995
1.00 3.00 3.00a 4.00 | 1.10 3.00 4.00
WINDOWS | MACINTOSH
The information in this article applies to: |
- Microsoft Project for Windows, versions 1.0, 3.0, 3.0a, 4.0 - Microsoft Project for the Macintosh, versions 1.1, 3.0, 4.0 |
Microsoft Project for Windows and Macintosh allows entry of two tasks that share the same name. This is not a design problem, but a feature. This feature allows for various situations such as summary tasks (e.g. pour concrete) to have the same name as tasks that fall beneath the summary tasks (e.g. pour concrete). In these cases, references made to either one of the tasks that share a name should be made using ID numbers.
KBCategory: kbhowto KBSubcategory:
Additional reference words: 4.00 1.0 1.00 1.1 1.10 3.0 3.00