Gantt Bar Draws over Nonworking Days
PSS ID Number: Q44578 Article last modified on 03-15-1995
1.00 3.00 4.00 | 1.10 3.00 4.00
WINDOWS | MACINTOSH
The information in this article applies to: |
- Microsoft Project for Windows, versions 1.0, 3.0, 4.0 - Microsoft Project for the Macintosh, versions 1.1, 3.0, 4.0 |
Microsoft Project for Windows and Macintosh draws Gantt bars from the start of a task to its end, including all nonworking days in between. Therefore, if a two-day task begins on Friday, the gantt bar will extend across Saturday, Sunday and into Monday.
KBCategory: kbhowto KBSubcategory:
Additional reference words: 1.0 1.00 1.1 1.10 3.0 3.00
Copyright Microsoft Corporation 1995.