Microsoft KB Archive/185293

From BetaArchive Wiki
Knowledge Base


PRJ98: Incorrect Timephased Baseline Cost in Usage View

Article ID: 185293

Article Last Modified on 1/23/2007



APPLIES TO

  • Microsoft Project 98 Standard Edition



This article was previously published under Q185293

SYMPTOMS

In Microsoft Project 98, task and assignment baseline cost may be incorrect in the Task Usage or Resource Usage view.

CAUSE

This behavior may occur when you save a baseline and the following conditions are true:

  • A task contains a split.

    -and-

  • A resource assigned to the split task has multiple rates on its cost rate tables.


WORKAROUND

To correct this problem, install Microsoft Project 98 for Windows Service Release 1 (SR-1).


STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, click the article number below to view the article in the Microsoft Knowledge Base:

185102 PRJ98: How to Obtain and Install MS Project 98 SR-1


Keywords: kbbug kbfix KB185293