Article ID: 185285
Article Last Modified on 1/23/2007
APPLIES TO
- Microsoft Project 98 Standard Edition
This article was previously published under Q185285
SYMPTOMS
In Microsoft Project 98, when you print or print preview a CrossTab report that includes cost or work information, costs or work assigned to summary tasks is not displayed.
CAUSE
Microsoft Project 98 does not display costs or work assigned to summary tasks in reports. This also applies to inserted project summary tasks, and project summary tasks.
RESOLUTION
To correct this problem, install Microsoft Project 98 for Windows Service Release 1 (SR-1).
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the article number below to view the article in the Microsoft Knowledge Base:
185102 PRJ98: How to Obtain and Install MS Project 98 SR-1