Article ID: 184005
Article Last Modified on 1/22/2007
APPLIES TO
- Microsoft Project 98 Standard Edition
This article was previously published under Q184005
SYMPTOMS
In Microsoft Project 98, if you edit information in the Resource Information dialog box, the resource's initials may be reset to an incorrect value.
CAUSE
This behavior occurs when a resource's initials are not the default, and you change some information in the Resource Information dialog box.
WORKAROUND
If possible, change resource information in a location other than the Resource Information dialog box. For example, to change a resource's Working Time, click Change Working time on the Tools menu. You can also change some additional resource information on the Resource Sheet.
If you need to change resource information in the Resource Information dialog box, re-enter the correct information in the Initials box.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the article number below to view the article in the Microsoft Knowledge Base:
185102 PRJ98: How to Obtain and Install MS Project 98 SR-1
Keywords: kbbug kbfix KB184005