SYMPTOMS
In Microsoft Project 98, some tasks in a project may display a split when a split is not expected.
CAUSE
This behavior occurs when you load a file created in Microsoft Project 4.O, and the task that displays the split has a percent complete greater than zero, is a fixed duration task, and has no resource assigned.
WORKAROUND
To work around this problem, change the duration of the task to zero. Then, reenter the original duration and percent complete.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).