== SYMPTOMS == | == SYMPTOMS == | ||
A field other than the one you selected appears next to a bar on the Gantt Chart. For example, if you attempt to show the '''Preleveled Start''' field next to a bar, the '''Resource Group''' field will appear instead. For a list of the fields that are affected by this behavior, see the | A field other than the one you selected appears next to a bar on the Gantt Chart. For example, if you attempt to show the '''Preleveled Start''' field next to a bar, the '''Resource Group''' field will appear instead. For a list of the fields that are affected by this behavior, see the "More Information" section of this article. | ||
</div> | </div> |
Latest revision as of 10:07, 21 July 2020
Article ID: 175022
Article Last Modified on 1/20/2007
APPLIES TO
- Microsoft Project 98 Standard Edition
This article was previously published under Q175022
SYMPTOMS
A field other than the one you selected appears next to a bar on the Gantt Chart. For example, if you attempt to show the Preleveled Start field next to a bar, the Resource Group field will appear instead. For a list of the fields that are affected by this behavior, see the "More Information" section of this article.
CAUSE
This behavior occurs whether you double-click a bar or use the Bar command on the Format menu to specify which field you want to appear next to the bar.
WORKAROUND
To work around this behavior, remove the bar formatting and then add text to the field by following these steps:
- Remove the bar formatting.
- Select the task with the bar formatting.
- On the Format menu, click Bar.
- Click Reset.
- Add text to the field.
- On the Format menu, click Bar Styles.
- Select the bar type you want.
- Click the Text tab.
- Add the field you want to appear.
- Click OK.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.
MORE INFORMATION
The following pairs of fields may exhibit this behavior:
Task Fields ----------- % Complete - Start9 % Work Complete - Finish9 Actual Cost - Cost9 Actual Duration - Start7 Actual Finish - Flag17 Actual Start - Flag16 Actual Work - Cost4 Assignment Delay - Confirmed Assignment Units - Update Needed Baseline Cost - Cost8 Baseline Duration - Finish6 Baseline Finish - Flag19 Baseline Start - Flag 18 BCWP - Date3 BCWS - Date4 Constraint Type - Date9 Contact - Cost Rate Table Cost - Cost7 Cost5 - Work Variance Cost6 - Remaining Work Cost10 - Fixed Cost Cost Variance - Date1 Created - Resource Phonetics Critical - Duration4 Date2 - Remaining Cost Date5 - SV Date6 - Name Date8 - WBS Duration - Finish7 Duration5 - Leveling Delay Duration6 - Free Slack Duration7 - Total Slack Duration8 - ID Duration9 - Milestone Duration10 - Priority Duration Variance - Start8 Early Finish - Flag13 Early Start - Flag12 Finish - Flag11 Finish1 - Number13 Finish2 - Number16 Finish3 - Number19 Finish4 - Text12 Finish5 - Text15 Finish8 - Remaining Duration Finish10 - Start Finish Variance - Number6 Flag1 - Text22 Flag2 - Text23 Flag3 - Text24 Flag4 - Text25 Flag5 - Text26 Flag6 - Text27 Flag7 - Text28 Flag8 - Text29 Flag9 - Text30 Flag14 - Late Finish Flag15 - Late Start Flag20 - Start Variance Marked - Text21 Number7 - Predecessors Number8 - Successors Number9 - Resource Names Number10 - Resource Initials Number11 - Text1 Number12 - Start1 Number14 - Text2 Number15 - Start2 Number17 - Text3 Number18 - Start3 Number20 - Text4 Preleveled Start - Resource Group Start4 - Text11 Start5 - Text14 Start6 - Subproject File Text5 - Text13 Text6 - Text16 Text7 - Text17 Text8 - Text18 Text9 - Text19 Text10 - Text20 Work - Work Contour Resource Fields --------------- Actual Cost - Update Needed Actual Finish - Baseline Work Actual Start - Actual Work Assignment Delay - Name Assignment Units - Initials Base Calendar - Confirmed Baseline Cost - Project Baseline Finish - Max Units Baseline Start - Group Code - TeamStatus Pending Cost - CV Cost Rate Table - Work Finish - Standard Rate Leveling Delay - Overtime Rate Overtime Work - Workgroup Response Pending - Text1 Start - Text2