Microsoft KB Archive/174345

From BetaArchive Wiki
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Article ID: 174345

Article Last Modified on 1/20/2007



APPLIES TO

  • Microsoft Project 98 Standard Edition
  • Microsoft Project 3.0 Standard Edition
  • Microsoft Project 3.0a
  • Microsoft Project 4.0 Standard Edition
  • Microsoft Project 4.1 Standard Edition
  • Microsoft Project 4.1a
  • Microsoft Project 3.0 for Macintosh
  • Microsoft Project 4.0 for Macintosh



This article was previously published under Q174345

SYMPTOMS

In Microsoft Project, when you enter dates for an existing task, the duration may not be calculated based on the dates entered.

CAUSE

This behavior occurs if the task is a milestone. Since the duration of a milestone is zero days, it will disregard one of the two dates you enter.

WORKAROUND

To calculate the duration, follow the appropriate steps for your situation:

Microsoft Project 98

  1. Select the task in Gantt Chart view.
  2. On the Project menu, click Task Information.
  3. In the Task Information dialog box, change Duration to 1d.
  4. Click OK.
  5. Repeat Steps 1 and 2.
  6. In the Task Information dialog box, re-enter the start and finish dates for the task. You must re-enter the dates even if one of them is correct.
  7. Click OK.

For Microsoft Project 4.0, 4.1, 4.1a

  1. Select the task in Gantt Chart view.
  2. On the Insert menu, click Task Information.
  3. In the Task Information dialog box, change Duration to 1d.
  4. Click OK.
  5. Repeat Steps 1 and 2.
  6. In the Task Information dialog box, re-enter the start and finish dates for the task. You must re-enter the dates even if one of them is correct.
  7. Click OK.

Microsoft Project 3.0 and 3.0a

  1. Select the task in Gantt Chart view.
  2. On the Edit menu, click Form.
  3. In the Task Edit Form dialog box, change Duration to 1d.
  4. Click OK.
  5. Repeat Steps 1 and 2.
  6. In the Task Edit Form dialog box, re-enter the start and finish dates for the task. You must re-enter the dates even if one of them is correct.
  7. Click OK.


STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

Keywords: kbbug kberrmsg kbpending KB174345