Article ID: 172909
Article Last Modified on 1/20/2007
APPLIES TO
- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
This article was previously published under Q172909
SYMPTOMS
If you set a task to 100% complete and then change the duration of the task, the percent complete will be distributed over the initial duration of the task rather than the new duration of the task.
CAUSE
Once you set a task to 100% complete, Microsoft Project will no longer perform calculations on it. The percent complete is calculated for the duration of the task at the time when it reaches 100%.
WORKAROUND
To recalculate the task, change the percent complete to a value other than 100%, such as 0% or 99%, and then change the percent complete back to 100%. The value should be calculated correctly.
Additional query words: prj2000
Keywords: kbbug kbpending KB172909