Microsoft KB Archive/172890: Difference between revisions

From BetaArchive Wiki
(importing KB archive)
 
m (Text replacement - """ to """)
 
Line 73: Line 73:
== MORE INFORMATION ==
== MORE INFORMATION ==


When you link a task where the predecessor task name and a resource name are identical, the relationship is based on the resource name rather than the task name. In the following steps, the result is that task "T2" will be linked to the task that has resource "A1" assigned to it rather than the actual task named "A1."
When you link a task where the predecessor task name and a resource name are identical, the relationship is based on the resource name rather than the task name. In the following steps, the result is that task "T2" will be linked to the task that has resource "A1" assigned to it rather than the actual task named "A1."
# Create a task called "X".
# Create a task called "X".
# Assign a resource to "X" called "A1."
# Assign a resource to "X" called "A1."
# Create two additional tasks, one called "T2" and the other called "A1."
# Create two additional tasks, one called "T2" and the other called "A1."
# On the '''View''' menu, click '''Task Usage'''.
# On the '''View''' menu, click '''Task Usage'''.
# Double-click the task named "T2" and click the '''Predecessor''' tab.
# Double-click the task named "T2" and click the '''Predecessor''' tab.
# In the '''Task Name''' field, type "A1" (do not select A1 in the drop-down list).
# In the '''Task Name''' field, type "A1" (do not select A1 in the drop-down list).





Latest revision as of 10:06, 21 July 2020

Knowledge Base


Article ID: 172890

Article Last Modified on 1/20/2007



APPLIES TO

  • Microsoft Project 2000 Standard Edition
  • Microsoft Project 98 Standard Edition



This article was previously published under Q172890

SYMPTOMS

You receive unexpected results when you link tasks if the name of the task and the resource are identical.

CAUSE

This problem occurs when using task usage view. In this view, Microsoft Project searches the Names column, and finds the assignment name before it finds the task name.

WORKAROUND

To work around this problem, change either the task name or resource name so that they are not identical.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

MORE INFORMATION

When you link a task where the predecessor task name and a resource name are identical, the relationship is based on the resource name rather than the task name. In the following steps, the result is that task "T2" will be linked to the task that has resource "A1" assigned to it rather than the actual task named "A1."

  1. Create a task called "X".
  2. Assign a resource to "X" called "A1."
  3. Create two additional tasks, one called "T2" and the other called "A1."
  4. On the View menu, click Task Usage.
  5. Double-click the task named "T2" and click the Predecessor tab.
  6. In the Task Name field, type "A1" (do not select A1 in the drop-down list).



Additional query words: prj2000