Article ID: 172729
Article Last Modified on 1/20/2007
APPLIES TO
- Microsoft Project 98 Standard Edition
This article was previously published under Q172729
SYMPTOMS
In Microsoft Project 98, if you select a task and then unlink the task, all predecessor and successor tasks (links) will be deleted. This applies to external predecessor and successor tasks as well as normal tasks. For example, if you select a task and then click Unlink Tasks on the Edit menu, all tasks linked to the task will be unlinked in both the source project and the active project.
RESOLUTION
To remove a predecessor or successor task, unlink the predecessor or successor task rather than the external predecessor or successor task.