PRJ98:Summary Fixed Cost Not Exported w/Analyzed Timescaled Data

Article ID: 170707

Article Last Modified on 1/20/2007



APPLIES TO

  • Microsoft Project 98 Standard Edition



This article was previously published under Q170707

SYMPTOMS

When you run the Analyzed Timescaled Data macro, Microsoft Project will send incorrect cost information to Microsoft Excel.

CAUSE

The Analyzed Timescaled Data Wizard does not send the fixed cost information assigned to Summary tasks to Microsoft Excel. Fixed cost information assigned to other tasks is sent to Microsoft Excel correctly.

WORKAROUND

To work around this problem, open or switch to the Microsoft Excel worksheet which contains the cost information and type the correct value in the cell that contains the incorrect total cost for the Summary task.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

Keywords: kbbug kbinterop kbpending kbusage KB170707