Microsoft KB Archive/170243

From BetaArchive Wiki
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Knowledge Base


PRJ98: Duration Times Round Up After Saving in Text Format

Article ID: 170243

Article Last Modified on 1/20/2007



APPLIES TO

  • Microsoft Project 98 Standard Edition



This article was previously published under Q170243

SYMPTOMS

Durations that have a decimal value will be rounded up when you open or save a file in the following formats:

  • Comma-separated variable text (.csv)


  • ASCII text (.txt)


  • Microsoft Project 4.0 format (.mpx)


CAUSE

This behavior occurs when the start and finish dates in the project file use a date only format rather than a date and time format. For example, this behavior occurs when you use a date format like this:

January 31, 1998
1/31/98


but the behavior does not occur when you use a date and time format like this:

January 31, 1998 12:33 PM
1/31/98 12:33 PM


WORKAROUND

To preserve decimal values in the durations for a task, use a date and time format for the start and finish times before you import or export the file. To do this, use the following steps:

  1. On the Tools menu, click Options, and then click the View tab.
  2. In the Date list, select a date format that contains the time. For example, click "1/31/98 12:33 PM".
  3. Click OK.


Keywords: kbbug kbinterop kbpending KB170243