Project: Cost Variance Formula Incorrect in FIELDS.WRI
PSS ID Number: Q110778 Article last modified on 10-14-1994
1.00 3.00 3.00a | 3.00
WINDOWS | MACINTOSH
The information in this article applies to: |
- Microsoft Project for Windows, versions 1.0, 3.0, 3.0a - Microsoft Project for Macintosh, version 3.0 |
SUMMARY
The FIELDS.WRI file in Microsoft Project for Windows 3.0 list the formula for CV incorrectly:
CV = BCWP - Actual Cost
The correct entry for this line is the following:
CV = Actual Cost - BCWP
NOTE: For more information on earned value, query on the following words in the Microsoft Knowledge Base:
Earned and Value
MORE INFORMATION
Microsoft Project 1.0 calculates Earned Value Cost Variance based on the formula:
CV = BCWP - Actual Cost (ACWP)
Microsoft Project 3.0 calculates Earned Value Cost Variance based on the formula:
CV = Actual Cost - BCWP
KBCategory: kbdocerr KBSubcategory:
Additional reference words: 1.00 3.00 3.00a doc error