Project: Valid Lead and Lag Values

PSS ID Number: Q109416 Article last modified on 03-15-1995

1.00 3.00 3.00a 4.00 | 1.10 3.00

WINDOWS | MACINTOSH

The information in this article applies to:
- Microsoft Project for Windows, versions 1.0, 3.0, 3.0a, 4.0 - Microsoft Project for the Macintosh, version 1.1 and 3.0

SUMMARY

The following is a list of valid time values that can be entered into the Lag field in Microsoft Project. Lead and lag time can be expressed in working time units or elapsed time units, or as a percentage or elapsed percentage of the duration of the predecessor task.

Working time Elapsed time
m=minutes em=elapsed minutes
h=hours eh=elapsed hours
d=days ed=elapsed days
w=weeks ew=elapsed weeks
%=%complete e%=elapsed %complete

Lag time is created by using a positive time value from the above list and lead time is created by using a minus sign before the time value.