Article ID: 101342
Article Last Modified on 1/18/2007
APPLIES TO
- Microsoft Project 98 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.1a
- Microsoft Project 1.0 Standard Edition
- Microsoft Project 3.0 Standard Edition
- Microsoft Project 3.0a
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 1.1 for Macintosh
- Microsoft Project 3.0 for Macintosh
This article was previously published under Q101342
SUMMARY
When you print a task view, such as the Gantt Chart or Task Sheet, it may appear that Microsoft Project is unnecessarily printing blank tasks following the last task shown in the view. This situation may occur when a task that was created inadvertently is still located in the task list.
One way you may inadvertently create a new task is by using a predecessor ID for a task that does not yet exist. When you enter predecessor information for a task, and if a task ID is entered for a task that does not yet exist, the task is automatically created.
Example
In a project with only 20 tasks, you enter "500" in the predecessor ID field for one of the tasks. Since task 500 does not yet exist, it is created. When you print a task view filtered for "All Tasks", tasks 1-500 (including all blank lines) will be printed.
To check for the existence of these additional tasks in a task view, do the following:
- In Microsoft Project for Windows, press CTRL+END.
- In Microsoft Project for the Apple Macintosh, press COMMAND+END.
This moves the current selection to the last task in the view. If this task should not exist, delete it (Delete from the Edit menu).
Additional query words: 3.00a
Keywords: kbinfo kbusage KB101342