Project 3.x: Cannot Level Tasks with a Rescheduled Duration
PSS ID Number: Q100510 Article last modified on 03-15-1995
3.00 3.00a | 3.00
WINDOWS | MACINTOSH
The information in this article applies to: |
- Microsoft Project for Windows, versions 3.0, 3.0a - Microsoft Project for the Macintosh, version 3.0 |
SUMMARY
Page 219 of the “User’s Reference” version 3.0, incorrectly states that leveling can occur on tasks where the remaining duration has been rescheduled.
Once a task has started (actual start date is set), the task can no longer be leveled.
KBCategory: kbdocerr KBSubcategory:
Additional reference words: 3.00 3.00a noupd
Copyright Microsoft Corporation 1995.