“Invalid Values” Error Message with Edit, Find
PSS ID Number: Q44655 Article last modified on 03-15-1995
1.00 3.00 3.00a 4.00 | 1.10 3.00 4.00
WINDOWS | MACINTOSH
The information in this article applies to: |
- Microsoft Project for Windows, versions 1.0, 3.0, 3.0a, 4.0 - Microsoft Project for the Macintosh, versions 1.1, 3.0, 4.0 |
SUMMARY
The error message “Invalid Values” when using the Edit, Find command normally means that you have requested that Microsoft Project find multiple values within a range that is separated by commas. Comma-separated values in an Edit, Find must be enclosed by quotation marks if the date format itself includes a comma. Eg., the date pair 2/3/89, 3/17/89 needs no quotes, but “Feb 3, 1989”, “March 17, 1989” does.
MORE INFORMATION
The following is the method for finding all the tasks (resources) within a date range based on Scheduled Start Dates with a single Edit, Find:
Field: Scheduled
Test: Within
Value: “Fri Feb 3, ’89”, “Fri Mar 17, ’89”
KBCategory: kbother KBSubcategory:
Additional reference words: 1.0 1.00 1.1 1.10 3.0 3.00 3.00a 4.00