Microsoft KB Archive/36558

From BetaArchive Wiki

Duration Scheduling in Project

PSS ID Number: Q36558 Article last modified on 10-20-1995

1.00 3.00 3.00a 4.00 4.10 | 1.10 3.00 4.00

WINDOWS | MACINTOSH

The information in this article applies to:
- Microsoft Project for Windows, versions 1.0, 3.0, 3.0a, 4.0 - Microsoft Project for the Macintosh, versions 1.1, 3.0, 4.0 - Microsoft Project for Windows 95, version 4.1

Microsoft Project supports two types of duration scheduling:

  1. Resource-driven scheduling
  2. Fixed-duration scheduling

In resource-driven scheduling, duration is determined by the amount of work to be done and the number of resources applied to the task. Project calculates by the formula Duration=Work/Units. Resource-driven scheduling is specified by choosing No in the Fixed field box on the Task Form (Fixed=N).

In fixed-duration scheduling, duration is not calculated from resource assignments. The Project Calendar is used with the duration to calculate the Scheduled Start and Scheduled Finish dates. Project calculates by the formula Work=Units*Duration. Fixed-resource scheduling is specified by choosing Yes in the Fixed field box on the Task Form (Fixed=Y).

KBCategory: kbusage KBSubcategory:

Additional reference words: 4.00 1.0 1.00 3.0 3.00

Copyright Microsoft Corporation 1995.