Article ID: 174803
Article Last Modified on 1/20/2007
APPLIES TO
- Microsoft Project 98 Standard Edition
This article was previously published under Q174803
SYMPTOMS
In Microsoft Project 98, if you type an ID for a predecessor task in Task Form view and the Predecessor field contains more than 255 characters, you will receive the following error:
NOTE: These symptoms occur with Successor tasks as well as predecessor tasks. In addition to Task Form view, this behavior also occurs in Task Details Form view and Task Name Form view.
CAUSE
This problem occurs if the data in the Predecessor field exceeds 255 characters.
WORKAROUND
To work around this problem, use either of the following methods.
Method 1
- Select the task.
- On the Project menu, click Task Information, and then click the Predecessor tab.
- Do either of the following:
- In the ID column, type the task id number
-or-
- In the Task Name column, select the Task Name of the predecessor.
- In the ID column, type the task id number
- Click OK.
Method 2
In Task Form view, in the Predecessors column, either type or select the Task Name of the predecessor.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.
Keywords: kbbug kbpending kbusage KB174803