Microsoft KB Archive/169237

From BetaArchive Wiki
Knowledge Base


PRJ98: Changed Baseline Values in Usage View not Updated

Article ID: 169237

Article Last Modified on 1/19/2007



APPLIES TO

  • Microsoft Project 98 Standard Edition



This article was previously published under Q169237

SYMPTOMS

When you attempt to update the Baseline Work or Baseline Cost in the right pane while you are in Task Usage view, they are not updated. Instead, the Budgeted Cost of Work Scheduled (BCWS) and the Schedule Variance (SV) are updated.

WORKAROUND

To work around this problem and update the Baseline Work or the Baseline Cost of a task, use the Baseline Table. To do this,

  1. On the View menu, point to Table, and then click More Tables.
  2. In the More Tables dialog box, click Baseline, and then click Apply.

You can now update the Baseline Cost or Baseline Work values for a task.


Additional query words: 98

Keywords: kbprb kbusage KB169237