PRJ98: BCWS Field Updated Incorrectly w/ Multiple Assignments

Article ID: 169236

Article Last Modified on 1/19/2007



APPLIES TO

  • Microsoft Project 98 Standard Edition



This article was previously published under Q169236

SYMPTOMS

When you assign three or more resources to a task and you use all three accrual methods, the result of the Budgeted Cost Work Scheduled(BCWS) field will be incorrect by one penny for each resource using the prorated resource accrual method.

WORKAROUND

To work around this problem, make sure that you are using no more than two resource accrual methods.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.


Additional query words: BCWS accrue multiple resources