Article ID: 169236
Article Last Modified on 1/19/2007
APPLIES TO
- Microsoft Project 98 Standard Edition
This article was previously published under Q169236
SYMPTOMS
When you assign three or more resources to a task and you use all three accrual methods, the result of the Budgeted Cost Work Scheduled(BCWS) field will be incorrect by one penny for each resource using the prorated resource accrual method.
WORKAROUND
To work around this problem, make sure that you are using no more than two resource accrual methods.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.
Additional query words: BCWS accrue multiple resources
Keywords: kbbug kbpending kbusage KB169236